What Is the Maximum Solar System Size Allowed by PECO? Expert Insights

Homeowners often ask me about the maximum solar system size allowed by PECO, especially after hearing an incorrect figure from a neighbor.

what is the maximum solar system size allowed by pecoI understand the confusion about how to get the most out of a solar system.

PECO doesn’t set the limit, and it won’t appear on your electricity bill. In other states, net metering eligibility is based on electricity consumption, but in Pennsylvania, it’s different.

Most homeowners who ask about system size really want to know how much of their energy costs they can cover before the utility company steps in. PECO customers almost always ask this way.

Since founding TerraSol in 2009, I’ve sized many residential solar systems in PECO’s coverage area. In my experience, the state limit is rarely the limiting factor in the number of solar panels that can be installed on a roof. There’s usually another factor that’s considered first.

I’ll share the numbers, their sources, and the limits that matter most when installing solar panels on a real home.

If you are just starting out, figure out how many panels you actually need first, then look at the cap later.

Quick Answer

The maximum solar system size allowed by PECO is 50 kilowatts of nominal capacity for residential customers and 3 megawatts for other accounts, as established by Pennsylvania law in the Pennsylvania Code, Section 75.13. Systems of 500 kW or more require approval from the Public Utility Commission (PUC). Most homes never come close to these limits

What Is the Maximum Solar System Size Allowed by PECO?

I hear this question on almost every first call, and the answer often surprises people. The residential solar limit is 50 kW, but this is not a PECO rule.

It is established by Pennsylvania law, specifically in Pennsylvania Code 52, Section 75.13, which sets the conditions for net metering for each electric distribution company regulated by the PUC.

solar energy systemPECO adheres to this standard and does not have a separate or stricter limit for residential customers.

Here is what the regulation says:

  • The nominal capacity of a solar power system in a home must not exceed 50 kW (as set out in Section 75.13(a)(3)).

  • In other properties, the limit is 3 MW (Section 75.13(a)(4)).

  • Any system of 500 kW or more requires Commission approval for net metering (Section 75.13(a)(5)).

  • Under the microgrid provisions set out in Section 75.16, systems with a capacity greater than 3 MW may net-meter up to 5 MW.

To give you an idea, most of the residential solar systems we design in PECO’s territory have a capacity of between 6 kW and 12 kW. You would need four to eight times as many panels as a typical system to reach the limit.

That amount of solar exceeds the typical capacity of a single-family home’s roof.

Since we founded TerraSol in 2009, I’ve seen only a few residential projects where the state limit was truly the issue. For reference, a 9 kW solar installation is roughly in the typical mid-range.

It’s important to note that the rated capacity refers to the AC output, which is the continuous AC power rating of your inverters.

For example, when a 13 kW DC system is connected to a 10 kW AC inverter, the system is considered 10 kW for grid connection purposes, and I make sure to verify the difference between the DC and AC power ratings if a project is approaching the limit.

SHOWCASE

Explore our commercial
solar installation projects

See how we can reduce
your energy costs

We have designed and installed solar systems for a range of auto dealerships. Discover how we can help you save.

Additional Information

PECO Does Not Limit Your System to Your Consumption.

I want to clarify this misunderstanding more than any other. I want to be clear because there is a lot of misinformation circulating, and you deserve to know the facts.

Pennsylvania does not limit the size of your residential system as a percentage of your annual electricity consumption. Many states do.

Pennsylvania does not. The Public Utility Commission (PUC) attempted to add a limit.

In February 2016, regulations were passed that would have limited net metering systems to 200% of a customer’s consumption.

On May 19, 2016, the Independent Regulatory Review Commission unanimously (5-0) rejected the package, finding that the PUC lacked the legal authority to impose such a limit. It never went into effect.

Legally, you can connect a system with more capacity than you need, but whether it’s in your best interest to do so is another matter, and my answer is NO.

The reason is that net metering credits, which you use to offset your own energy consumption, have the same value as the retail rate.

Any credits you don’t use remain as accumulated credits until the end of the metering year on May 31, and any surplus generation that PECO hasn’t yet applied to your account is paid at the price-to-compare, which is the generation supply amount shown on your bill, not the full retail price.

If your system produces more energy than you consume each year, you end up selling that surplus electricity at a lower price than you pay for it. Therefore, building a larger system doesn’t always result in savings.

When choosing the right size, I recommend basing your decision on your actual kilowatt-hour consumption and any clearly identifiable loads — for example, if you plan to buy an electric vehicle in the next two years.

Our guide to residential energy storage explains how storage affects system sizing.

System size determines which interconnection application you should submit. Pennsylvania’s interconnection rules, in Pennsylvania Code 52, section 75.34, establish four tiers, and PECO publishes the rates and review periods for each:

LevelSystem sizeFeeReview window
Level 110 kW or less, certified inverter-based$10025 business days
Level 211 kW to 2,000 kW, certified inverter-based$250 plus $1 per kW30 business days
Level 310 kW to 50 kW, non-inverter$350 plus $2 per kWVaries
Level 450 kW or less, non-exporting$350 plus $2 per kWVaries
Most residential solar systems are classified as Tier 1; If your system exceeds 10 kW, it will move to Level 2, which involves a higher tariff, a longer review process, and a more thorough engineering examination of your distribution circuit. That’s where I review the design details. Although a 10.2 kW system and a 9.8 kW system differ only in their power rating, they require different documentation. In some cases, the additional power justifies the extra steps, and in others, it doesn’t. The decision should be deliberate, not arbitrary, which is why I object to quotes that state the system size without simultaneously showing the corresponding interconnection level.

State limits are almost never the limiting factor. The factors that truly limit size are:

Usable roof area. South-, southwest-, and southeast-facing surfaces must be free of chimneys, vents, and dormers. In most homes, this is the binding limit.

Shading. Tree cover is dense in Chester, Delaware, and Montgomery counties. Module-level electronics recover some of the lost energy, but not all of it.

peco local solar incentivesElectrical service. The capacity of your main panel’s busbar and the National Electrical Code’s 120% rule determine how much solar power it can accommodate. A 100-amp service will limit a system long before the state does. This is the most common reason for downsizing or upgrading the service.

Roof condition. If your roof has less than ten years of remaining life, it’s best to address any issues before installing panels. Removing and reinstalling a panel array later is costly.

Your circuit. PECO reviews the connection capacity of your specific feeder. On an overloaded circuit, a larger system may require upgrades.

This is one reason why Tier 2 reviews take longer. I prefer to design a system tailored to your home and electrical service, rather than simply looking up a value in a spreadsheet.

When I assess a property’s solar potential, I review this list during the site visit, and the 50 kW limit rarely comes up.

Design decisions also impact long-term production, a topic we cover in our guide to maximizing your solar energy system.

State limits are almost never the limiting factor. The factors that truly limit size are:

Usable roof area. South-, southwest-, and southeast-facing surfaces must be free of chimneys, vents, and dormers. In most homes, this is the binding limit.

Shading. Tree cover is dense in Chester, Delaware, and Montgomery counties. Module-level electronics recover some of the lost energy, but not all of it.

peco local solar incentivesElectrical service. The capacity of your main panel’s busbar and the National Electrical Code’s 120% rule determine how much solar power it can accommodate. A 100-amp service will limit a system long before the state does. This is the most common reason for downsizing or upgrading the service.

Roof condition. If your roof has less than ten years of remaining life, it’s best to address any issues before installing panels. Removing and reinstalling a panel array later is costly.

Your circuit. PECO reviews the connection capacity of your specific feeder. On an overloaded circuit, a larger system may require upgrades.

This is one reason why Tier 2 reviews take longer. I prefer to design a system tailored to your home and electrical service, rather than simply looking up a value in a spreadsheet.

When I assess a property’s solar potential, I review this list during the site visit, and the 50 kW limit rarely comes up.

Design decisions also impact long-term production, a topic we cover in our guide to maximizing your solar energy system.

Understanding the credit system is crucial for making an informed decision about system sizing, so familiarize yourself with it before signing any documents:

PECO installs a bidirectional meter that records the energy you draw from the grid and the energy you feed back.

The energy your solar panels export generates a credit per kWh at the full retail rate.

Excess kWh accumulate month by month during the billing period at that full retail rate.

At the end of the metering year, on May 31, PECO compensates the system owner for any remaining net metering credits at the price-to-compare rate.

Net metering does not eliminate your monthly charge. Grid-tied solar energy reduces your electricity bill, but it doesn’t eliminate the bill.

Your rate remains the same after the system is installed. The credits on your bill are reflected on the consumption side, not as a separate check each month.

pa solar company

A practical tip based on experience: if you’re comparing energy supply prices, check how your provider handles net metering before installation. Terms can vary, and it’s much easier to verify them upfront than to troubleshoot afterward.

It’s also important to clarify this because people often share information with friends in other areas. These rules are set by the Public Utility Commission (PUC) and apply to regulated electric distribution companies, such as PECO and Duquesne Light.

If your electricity comes from a municipal electric company or a rural electric cooperative in Pennsylvania, check directly with your provider about their specific program.

Review the rules regarding virtual net metering for commercial solar, which allows a single account to distribute its generation across multiple meters.

We published this one back in September 2012, and I keep coming back to it. It is a residential system in Glen Mills, Delaware County, inside PECO’s territory. As published, the project is:

  • System size: 3.8 kW

  • Type: grid-tied, roof-mounted

  • Modules: SOLON 235 W

  • Inverters: Enphase microinverters

The equipment is outdated. SOLON modules are not what we install today, and 235 W is significantly less than a current panel. The limitation that shaped the project hasn’t changed, so the example remains valid.

That system has a power output of 3.8 kW against a 50 kW limit. It consumes less than 8% of what Pennsylvania allows. The state limit was never mentioned during the project because it was never relevant.

The homeowner, Dave S., explained his system better than I could:

“We are thrilled with our new system! We wish we had a bigger roof so we could cover 100% of our energy needs. Terrasol did an excellent job and even helped us with the roof replacement.

They installed microinverters because half the system faces southwest and the other half southeast. We can monitor it online and see our energy performance. Save green energy!”

Read the second sentence again, because it sums up the entire article in one line. He wanted to cover all his electricity needs.

Pennsylvania would have allowed more than thirteen times the capacity he installed. What stopped him was the roof area.

The rest of his comment shows how the roof affects the equipment’s performance. Two usable planes facing opposite directions mean that the halves reach peak performance at different times of day, and a single-string inverter would have caused the entire system to respond to its weakest section.

Microinverters were the solution for your roof, not for a regulation. The roof replacement was done as part of the work, which is the right thing to do, since installing a system on a roof with only a few years of remaining lifespan means paying to remove and reinstall it later.

If your project exceeds these limits, it’s not a dead end, but rather a different category.

  • 500 kW or more: you may still qualify for net metering, but PUC approval is required. Factor additional time into your schedule.

  • For production above 3 MW, net metering up to 5 MW is available only if the system meets the requirements of Section 75.16.

  • Above 5 MW, systems fall outside net metering. They are connected as commercial generators, subject to different regulations and monetization methods.

For commercial customers, such as warehouses, car dealerships, and school campuses, the 3 MW limit is quite generous; I haven’t found any rooftops in the PECO coverage area that come close to it.

If you are in that position, our guide on commercial solar for businesses in Pennsylvania brings together the regulations, depreciation treatment, and financing options all in one place.

 

Two factors have changed the numbers, and I want to be transparent about them.

The federal tax credit under Section 25D has expired for expenses after December 31, 2025. Homeowners installing solar energy now cannot claim it, which means the upfront cost is higher than in 2024 and 2025.

The good news is local. PECO is offering a $500 rebate per system to residential electric customers with an approved interconnection application. This program will be in effect from June 1, 2026, through December 31, 2031.

You should check the eligibility criteria. Any system with a capacity up to 50 kW is eligible for the rebate, which is in line with the state’s net metering limit.

We explain the timelines and steps to take in our article on the PECO solar rebate extension. Because funds are limited and the program may change, you should verify your situation before relying on it. You can also explore other solar incentives to save money.

grid tied solar costThe alternative energy credit market in Pennsylvania is still active, allowing system owners to earn ongoing income from solar production in addition to saving on their bills. There are various financing options, such as loans, leases, and power purchase agreements, which should be compared to paying in cash.

I have expressed my opinion on the choice between buying and leasing solar panels, and it is not an unbiased opinion. Because solar incentives vary by municipality and utility company program, you need to research the incentives applicable to your household rather than relying on a statewide figure.

In my opinion, solar energy remains a viable option for many homeowners in the PECO area, especially when the system is tailored to their actual consumption and energy-efficiency improvements are prioritized. Reducing energy consumption is less expensive than producing more energy.

You should use the current figures, not those from the 2024 proposal, as a basis. If the figures are not suitable, I will let you know, and we can explore other solar energy options for a different timeframe.

Speak with someone who handles these applications.

I come from the finance industry and still view every project as an investment. This means I’ll let you know when a larger system isn’t cost-effective and show you the grid connection tier before you commit to a design.

TerraSol Energies is a family-owned solar energy company based in Chadds Ford, Pennsylvania. We’ve been installing solar systems in Pennsylvania, New Jersey, Delaware, and Maryland since 2009, and we’re exclusively dedicated to renewable energy.

We’re a PECO Certified Business Partner and an Enphase Gold Installer, and we personally handle the grid connection application, coordination with the utility company, and inspections. This is important for new residential solar installations, as managing the paperwork is where most PECO solar projects lose weeks.

Whichever company you hire, our guide to comparing solar installers will help you analyze quotes objectively.

Call (888) 873-9995 or request a free evaluation. We’ll analyze your energy consumption, model your roof, and answer the one question that will help you pay your bill: not what the maximum solar system size allowed by PECO is, but what the right size is for your home.

Enphase - Assets_Platinum_linear_edit
Trusted solar services:
TerraSol is a top-ranked solar company in the tri-state area.

Frequently Asked Questions

What is the maximum solar system size allowed by PECO?

50 kW nominal capacity at a residential service location and 3 MW at other locations, according to Pennsylvania Code 52, Section 75.13. Systems of 500 kW or more require approval from the Public Utility Commission (PUC) for net metering.

AC. The nominal capacity refers to the continuous AC capacity of your inverters. The total capacity of your DC panels can be higher.

Yes. Pennsylvania does not have a consumption-based limit for residential customers. A 2016 proposal for a 200% cap was rejected by the Independent Regulatory Review Commission (IRRC). However, excess generation remaining after the annual adjustment is paid for at the price-to-compare, not the retail rate, so oversizing your system does have a cost.

10 kW or less with certified inverter-based equipment. The fee is $100, and the review period is 25 business days.

Yes. $100 for Tier 1, $250 plus $1 per kW for Tier 2, and $350 plus $2 per kW for Tiers 3 and 4.

May 31. Any remaining accumulated credits on that date are redeemed at the price-to-compare.