Solar Panel Reinstallation: Cost, Permits & Process

Solar panel reinstallation is the call I get most often from homeowners who didn’t buy their system from us, and I’ve been using it at TerraSol since 2014.

The formula is almost always the same. The roofer will walk through the property, give you the number for the new roof, and then say something like, “And you’re going to need someone to take care of the panels.”

At that point, people call me, usually a little annoyed because no one mentioned this part when they bought the system.

It’s a routine job. Your roof needs fixing. The solar panels are bolted to it, so they need to be taken off and put back on.

What people worry about isn’t the job itself. It’s the order in which things are done, who can touch what, and the paperwork that needs to be done before your system can legally be turned back on.

No one plans for it the day of the solar panel installation. The roof and the array are on different clocks, and sooner or later those clocks will collide.

My background is in finance, not roofing. I came into solar with an investment in mind, and that’s how I view the job. Reinstallation is money you spend to protect an asset you already own. Having a setup like this makes the decision easier.

So let me give you a rundown of what’s going on, how much it costs, and two or three things I would check before letting someone on your roof.

Quick Answer

Reinstalling solar panels involves removing your existing rooftop solar system to allow work on the roof, then installing and reconnecting the same panels.

Solar panel costs are around $200 to $300 per panel, which works out to about $1,500 to $6,000 for a typical home. First, you need a permit, an electrical inspection, and a review of your warranties.

solar panel reinstallationWhat is Solar Panel Reinstallation?

Solar panel reinstallation is the process of removing an existing rooftop solar system from a roof to allow work to be done on the roof, then reinstalling and reconnecting the same panels. This is called disconnect and reconnect, or R&R for removal and reinstallation.

In practice, this means we shut down the system, remove the panels, dismantle the racking system, store everything, and then put it back together after the roofing work is complete.

You’re not buying a new solar system. You’re paying for labor, wiring, new fasteners and sheet metal, and the permitting and inspection required to legally get the system back up and running. This last part is often overlooked.

Think of it as the back half of the solar installation process that you’ve already gone through. There’s no design phase or equipment order, because the solar panel system is already yours. What is repeated is the installation, wiring, inspection, and documentation for utilities.

SHOWCASE

Explore our commercial
solar installation projects

See how we can reduce
your energy costs

We have designed and installed solar systems for a range of auto dealerships. Discover how we can help you save.

Additional Information

When do you need to remove and reinstall solar panels?

Removal and reinstallation are required whenever the roof under the solar panels needs to be replaced or repaired, as the area needs to be cleared so it is free.

The decision to make is not whether to do it, but whether to replace the entire roof once the panels are removed.

pa solar panel installation companiesHere is a conversation I have with almost everyone.

Asphalt roofs typically last around 30 years, and metal or tile roofs can last well over 50 years. Solar panels come with a 25-year warranty and typically last even longer. Industry guidelines make this clear, recommending replacing an asphalt roof that is 10 or more years old before installing solar panels on it.

It is this mismatch that is causing this problem. If your roof had 12 years left when the solar panels were installed, you were always going to end up here.

Most people I talk to had their solar panels installed sometime between 2012 and 2018, on a roof that wasn’t new at the time, and the bill for that timing is coming in now.

So if you’re getting quotes for a roof replacement, ask yourself how long your roof actually has. If the answer is “somewhat, maybe,” get the roof done now, while the panels are already coming down. I’m trying to discourage people from paying for two removals and reinstallations in a decade.

If you’re reading this before you’ve even had solar installed, the lesson is the same, but in reverse. Get the roof done first. We worked with a homeowner in Chester County who replaced an aging asphalt roof with a metal roof before we installed anything, and the clamp-based mounting system the roof allowed for meant there were no roof penetrations.

This sequence should be repeated if you still have the option.

The reinstallation process is a six-step process: shutdown and disconnect, tagging and dismantling the panels and racks, storing the equipment, completing the roof work, reinstalling and reconnecting, and then reconnecting to power and inspecting.

The first three and last two steps are performed by the solar company, and the roofer works in between.

  1. The solar company shuts down the system and disconnects it from your electrical panel.

  2. The panels, microinverters or optimizers, cabling, and racks are removed and tagged.

  3. Everything is safely stored.

  4. The roofers perform the removal and new roof on the open deck.

  5. The solar company reinstalls the racks with new sheet metal, returns each panel to its mapped position, and reconnects them according to regulations.

  6. The system is then turned back on, inspected, and tested.

This sequence follows a standard industry process and is how field work is done.

Two things I want to mention in this list.

Labeling matters more than it seems. Each panel will go back to its original location and chain. When workers skip the labeling step, the panels will go back to the wrong locations, which will cause the monitoring to no longer match the physical layout, and the homeowner will not be able to tell which panel is malfunctioning two years later.

It costs nothing to do it right, and the subsequent repair is annoying.

Don’t reuse the old brackets. New roof, new sheet metal, new fasteners. I’ve seen workers put racks back in old penetrations to save an hour. That’s the leak you’ll be arguing with two contractors about next spring.

local utility company in paThe solar company should remove the panels and put them back in, and the roofer should treat the roof. This isn’t a turf issue, it’s an electrical issue. Removing and reconnecting solar panels requires licensed electricians, and the roofing crew is not licensed to do this.

The problems I see with these projects are almost never technical. It’s about planning. The roofer shows up on Tuesday and the panels are still on the roof, or the panels come off and the roofing crew is out of commission for three weeks and your system is sitting on the ground in darkness while your electric bill is at full price.

This downtime is more expensive than it used to be, given where PECO’s electric rates are headed. Either hire a solar installer to coordinate the work directly with your roofer, or get the two companies on a single, shared schedule before anyone else starts.

I also tell people to call their original solar installer first. Whoever installed your system already knows the racks, the chain layout, and the mounting method, and can cover the work under warranty or price it lower.

If the company no longer exists, which is often the case with systems sold in the 2010s, then find someone else. Just ask first.

Published data suggests that reinstalling solar panels runs about $200 to $300 per panel, which is about $1,500 to $6,000 for a typical residential system with 15 to 25 panels. Larger or more complex jobs can exceed $7,000.

These figures vary quite a bit across sources:

  • About $200 to $300 per panel, with larger jobs exceeding $7,000.

  • About $1,500 to $6,000 for a residential system with about 15 to 25 panels.

What affects your price?

  • the number of panels

  • the pitch and height of the roof

  • the type of racking system

  • how long the panels are stored

  • municipal permit fees

  • any electrical work required by current regulations

Get a quote for the reinstallation and a separate quote for the roof, both in writing. Ask the solar company directly if the price includes new sheet metal and mounting hardware. If the quote is significantly below the range above, it is usually what was left out.

One more thing about money, because I look at this as a financier. Reinstallation does not add new solar savings. It protects the savings you already have.

Consider the solar costs versus what your solar panels cost you originally and how much they have returned to you since then, not versus zero.

For a system that has been running for eight or ten years, a few thousand dollars to keep it producing for another fifteen years is usually an easy decision.

Contact us at (888) 873-9995 for a more accurate estimate.

Yes. Rewiring a solar system is a licensed electrical installation, and jurisdictions in Pennsylvania generally require a building permit and an electrical permit under the state’s Uniform Construction Code, as well as a third-party electrical inspection before the utility company will allow the system.

Homeowners want to skip this part, and I understand why, but it’s not optional.

Pennsylvania jurisdictions generally require a building permit and an electrical permit under the state’s Uniform Construction Code.

save money for solar installationPhiladelphia has a simplified path for residential systems of 10 kW or less in a single- or two-family home that is not listed on the Philadelphia Register of Historic Places.

The ordinance has also changed. Pennsylvania adopted the 2020 National Electrical Code effective July 13, 2025, with full enforcement beginning January 12, 2026, and the 2021 International Codes went into effect January 1, 2026.

If your system was commissioned under an older cycle of regulations, it may be necessary to reinstall to meet current requirements. Quick shutdown, tagging, and disconnecting are common steps.

You will also need a third-party electrical inspection certificate and a certificate of completion, per PECO’s interconnection guidelines, before your system can be authorized by your utility.

One more thing. If anything changes during the system’s reinstallation — number of panels, inverter model, capacity, or layout — call your local utility company to ask if your grid interconnection and metering agreement needs to be updated.

Reinstalling the same type and a modified system are handled differently. PECO’s Green Power Connection team is available at 833-732-6334 or email GPCTeam@peco.com.

Protect your net metering agreement. This agreement credits you with the excess solar energy your system sends back to the utility, and it’s often the most valuable asset associated with an older solar energy system.

Changing capacity without telling anyone causes people to accidentally renegotiate terms they were happy with.

solar physical installation costIf you have a solar lease or power purchase agreement, you don’t own the equipment and you can’t hire your own crew to move it. The third-party owner controls what happens to the panels, so the removal and reinstallation must go through them.

This is what people are interested in. Under the lease, the panels belong to that company and they will take care of the removal at the end of the term at no cost to you.

Mid-term roof work is a different matter and depends on your contract. Read it or call them before you hire a roofer. You may not be allowed to hire your own crew.

If you paid cash or used a solar loan, you own the system and the decision is yours. If you’re not sure where you stand, or are considering both for your future system, I’ve written a longer article about what ownership actually changes versus leasing.

This also comes up when people sell. Reinstalling a leased solar array right before it goes on the market is a hassle that’s worth getting clear on ahead of time, and we’ve covered the math for buying out a solar panel lease when selling a home separately.

It can. There are three separate warranties covering this job; they are from three different companies, and a poorly done reinstall can affect all three.

Panel manufacturer. Removing and reinstalling panels can void the manufacturer’s warranty if the work isn’t done to specification by a qualified installer. Check your specific terms.

Solar system installation. Most installers will provide a warranty on the roof area around their mounts. Once someone else removes this hardware, this coverage may not follow.

New Roof Warranty. Your roofer’s warranty may be affected by how the solar mounts are re-pierced and flashed. Have the roofer and solar company agree in writing on the mounting method before installing the new roof.

This requires one email and will prevent a fight where one person points fingers at the other.

Keep your invoices and ask for photos of the mounts and flashing before you reinstall the panels. If you ever have a claim, it’s the documentation that will settle it.

No. The federal residential clean energy tax credit under Section 25D does not apply to expenditures made after December 31, 2025, so no federal solar energy tax credit can be claimed for a reinstallation done now.

This change came from Public Law 119-21, signed into law on July 4, 2025, which moved the expiration date from 2034 to the end of 2025 (26 U.S. Code 25D).

I mention this because homeowners ask this question all the time, and because reinstallations have never been a strong candidate for the credit anyway. You are relocating solar equipment that you already own, and there are no new qualified expenses.

financing options in paTalk to your tax advisor about your own situation rather than taking the word of contractors, including myself.

Local incentives are a separate issue. Financial incentives from state programs and energy companies change on their own schedules, so check what’s current in your municipality before making any assumptions.

For example, PECO’s $500 residential rebate runs through 2031 with its own application deadlines, though it applies to new systems rather than retrofits.

If the loss of the federal credit has made you reconsider solar in general, it’s a legitimate question, and I’ve answered it in detail our blog about the end of the tax incentive doesn’t mean the end of residential solar.

Net metering and SRECs haven’t gone anywhere, and SREC markets still pay you to support renewable energy generation from a system you already own.

It’s worth putting it bluntly: Incentive programs come and go, but the panels on your roof are still generating solar power one way or another. Reinstallation protects an asset that produces clean energy, no matter what the tax code does this year.

Before removal day, do a brief site assessment with your solar specialist and write down how the system performed before. This baseline is how you will prove that the panel will perform the same way afterward.

Record three things:

Baseline power output. Pull the monitoring data and record how much electricity the system was producing per panel, along with recent utility bills and your home’s energy usage. Compare after you reinstall the panels.

The reinstalled panels should generate as much electricity as before, taking into account the season and weather. A panel that returns to half its previous output will be stuck in the first week instead of the next year.

Record the electricity produced in the twelve months prior to removal. This single number will settle most disputes later, as it turns “system feels bad” into a number that the installer has to explain.

certified installers in paIf your electricity production was already lower than you expected before the roof work, the problem isn’t the reinstallation, and our notes on how to get more power from your existing solar power system are a better starting point.

Condition of the electrical panel and meter. The solar company should look at your electrical panel, disconnects, and meter while the system is down. If there’s anything that needs fixing, it’s the cheapest time in the next decade.

Add anything you want. The array is off, the roof is open, and the team is already on site. If you’ve been considering solar batteries, additional rooftop panels, or energy efficiency upgrades to your home’s attic, price them out now.

Doing these things later means paying for access twice. The most common question people ask about is energy storage, and we have been through the process of adding energy storage to an existing solar system for a Delaware County homeowner who was in the same situation.

Ask your installer what a “return to normal” looks like in writing, including the expected energy production and the date they will confirm it. A solar company that doesn’t include this in the scope is telling you something.

  • Reinstallation is a detach and reset — same panels off, roof done, panels back on. You pay for labor, hardware, permits, and inspection, not new equipment.

  • Budget $200 to $300 per panel, or $1,500 to $6,000 for a typical home.

  • The solar company handles the panels, the roofer handles the roof. Most problems are scheduling, not technical.

  • Permits are not optional. PA requires building and electrical permits plus a third-party inspection.

Talk to Us Before the Roofer Shows Up

TerraSol Energies has been a family-owned solar company in Chadds Ford since 2009, serving Pennsylvania, Delaware, New Jersey, and Maryland.

We are a PECO Certified Trade Ally, and our solar panel maintenance services include roof integrity inspections, panel repairs and replacements, electrical inspections, and warranty support.

If you have a quote for a roof on your desk and solar panels on your roof, call before you sign it. Making a decision on your order on the first call will save you money.

Call (888) 873-9995 or request a consultation, and we will discuss your options for solar panel reinstallation.

Enphase - Assets_Platinum_linear_edit
Trusted solar services:
TerraSol is a top-ranked solar company in the tri-state area.

Frequently Asked Questions

How long does it take?

The removal and reinstall are usually each a one-day scope for a standard home. The calendar time is driven by permits and inspection scheduling, not by the labor.

No. A tear-off requires a clear deck, and the panels must be de-energized by a qualified person.

Yes, if the work is done properly. Panels are durable and are routinely reinstalled. Check your monitoring app panel by panel once the system is back on, not just the system total.

Generally yes. Reconnecting a solar system is licensed electrical work, and Pennsylvania jurisdictions typically require building and electrical permits plus a third-party inspection.

It can. Confirm your panel manufacturer’s terms and your installer’s workmanship terms before work starts.

Ask for the license, ask whether they carry certification from the North American Board of Certified Energy Practitioners, and ask who pulls the permits. If the answer to that last one is “you do,” keep calling. Solar panel installation companies that handle their own permitting will handle your inspection too.

No. The federal residential clean energy credit does not apply to expenditures made after December 31, 2025. Check with your tax professional about any state or local incentives that still apply.

Plan on a few weeks from removal to final inspection on a typical residential solar job. The labor is short, the permit and inspection scheduling is what stretches it.